January 19, 2012 Fairways Update

 

Section 1 is complete. 

Section 2 has curbs poured; however part of Section 4, a portion of Big Spur & three courts behind the 7-11, were added to Section 2 and have been milled and curbs will be installed next week.  Then paving will begin in Section 2 and this extra portion. 

 Section 3 will begin within next 21 days weather permitting.

 

 